The following streets will be milled and paved as part of our upcoming 2023 program. Dates are subject to change, and weather dependent. Affected residents will receive a door hanger with instructions several days in advance notifying them that the work will be starting. All paving work should be completed by mid-September.
Hedgerow Lane - Mill 8/25, 8/28, 8/29. Pave - 8/30, 8/31, 9/1
Split Rock Road - Mill 8/25, 8/28, 8/29. Pave - 8/30, 8/31, 9/1
Royal Hunt Way - Mill 8/31, 9/1, 9/5. Pave - 9/7, 9/8, 9/11
Sovereign Circle - Mill 8/31, 9/1, 9/5. Pave - 9/7, 9/8, 9/11
Squire Lane - Mill 8/31, 9/1, 9/5. Pave - 9/7, 9/8, 9/11
Marquis Court - Mill 8/31, 9/1, 9/5. Pave - 9/7, 9/8, 9/11
Harvest Drive - Mill 8/29, 8/30, 8/31. Pave - 9/5, 9/6, 9/7
Olde Field Drive - Mill 8/30, 8/31, 9/1. Pave - 9/6, 9/7, 9/8
Farmstead Lane - Mill 8/29, 8/30, 8/31. Pave - 9/5, 9/6, 9/7
Springside Drive - Mill 8/29, 8/30, 8/31. Pave - 9/5, 9/6, 9/7
Fieldstone Court - Mill 8/29, 8/30, 8/31. Pave - 9/5, 9/6, 9/7
Barley Drive - Mill 8/29, 8/30, 8/31. Pave - 9/5, 9/6, 9/7
Thresher Court - Mill 8/30, 8/31, 9/1. Pave - 9/6, 9/7, 9/8
Camelia Court - Mill 9/5, 9/6, 9/7. Pave - 9/11, 9/12, 9/13
Hibiscus Court - Mill 9/5, 9/6, 9/7. Pave - 9/11, 9/12, 9/13
Gardenia Court - Mill 9/1, 9/5, 9/6. Pave - 9/8, 9/11, 9/12
Ridings Way - Mill 9/1, 9/5, 9/6. Pave - 9/8, 9/11, 9/12
Tiffany Drive - Mill 9/1, 9/5, 9/6. Pave - 9/8, 9/11, 9/12
Farnum Road - Mill 9/1, 9/5, 9/6. Pave - 9/8, 9/11, 9/12
Crestmont Court - Mill 9/1, 9/5, 9/6. Pave - 9/8, 9/11, 9/12
Rosemont Drive - Mill 9/5, 9/6, 9/7. Pave - 9/11, 9/12, 9/13
Dogwood Drive - Mill 9/5, 9/6, 9/7. Pave - 9/11, 9/12, 9/13
Heatherstone Way - Mill 8/28, 8/29, 8/30. Pave - 9/1, 9/5, 9/6
Ryan Path - Mill 8/28, 8/29, 8/30. Pave - 8/31, 9/1, 9/5
Glendower Drive - Mill 8/28, 8/29, 8/30. Pave - 8/31, 9/1, 9/5
Pickering Trail - Mill 8/28, 8/29, 8/30. Pave - 9/1, 9/5, 9/6